Highland Glen Electric Reliability Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2021-05-19
Anticipated End Date: 2021-07-07

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

NOTE: In some circumstances, weekends and extended hours may be required. 

Project Objective

JEA has completed work to upgrade the electrical equipment that serves the Highland Glen area. A contractor working for JEA (Heart Utilities, Inc.) installed new electric conduit, cables, and manholes. The contractor installed the new conduit with a technique called horizontal directional drilling (HDD). HDD requires very little excavation, reduces construction duration, and is less disruptive to the surrounding community. This project will help to proactively improve the overall quality and reliability of your electric service. 

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights of way, roads and easements.  

Work Area Map

Highland Glen Electric Reliability Improvement Project

Restoration of Project Area

Restoration of the project area will typically begin 2-3 weeks after the project has been completed. Any existing grass, sprinklers, pavement, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.