Holiday Harbor Electric Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-04-20
Anticipated End Date: 2020-08-31

Monday through Friday, 7:00 a.m. to 5:00 p.m.

Note: In some circumstances, weekends and extended hours may be necessary. 

 

Roads Affected

Blackbeard Drive, Captain Hook Drive North, Captain Hook Drive West, Castaway Drive, Cove Lane, Island Cove Drive, Lookout Place, Peg Leg Road, Seafarer Drive, Treasure Cove Lane

Project Objective

A contractor working for JEA (Heart Utilities, Inc.) completed work to install new conduit, cabling, transformers and PVC manholes in Holiday Harbor area. This involved underground boring and pulling in of the new cables. This project will help to improve the overall quality and reliability of electric  service in the area. 

Construction Conditions & Restoration of Project Area

Most of the construction activities occurred in the City of Jacksonville right-of-way portion, usually closer to the sidewalk or road. Any grass, concrete, asphalt, or sprinklers damaged during the work will be replaced after the completion of the project.  

Project Area Map

Holiday Harbor EIP Project Area Map