Indian Walk Road Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-04-12
Anticipated End Date: 2023-05-12

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, evening hours and weekends may be required.

Project Objective

JEA crews replaced a portion of failing sanitary sewer line on Indian Walk Road between Autumn Valley Road and Arrowhead Drive. This work was necessary to ensure the reliability of the sewer system that serves your neighborhood. Failures to sewer lines can potentially cause major sewer back-ups, environmental harm and roadway issues.

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.

Indian Walk Sewer Project Map

Restoration of the Project Area

Restoration of the project area typically begins approximately 2-3 weeks after the sewer main has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their pre-construction condition.