- Home
- In Our Community
- Construction Projects
- JEA Kennedy Generation Station Site - Corrective Measures Study
JEA Kennedy Generation Station Site - Corrective Measures Study
![](https://www.jea.com/uploadedimages/Images/ConstructionProjectDefaultBanner.jpg)
Estimated Dates & Work Schedule
Anticipated End Date: 2020-12-31
These dates are strictly projections as this project is in the preliminary study and design phase. It is estimated that it will take approximately three to four years to complete design, contracting and construction of the proposed remedy. These dates are highly subject to change due to design complexities, permitting, construction, and other unforeseen conditions.
JEA will continually update the status of this project on this web page.
Project Objective
Site Description & JEA History
The KGS consists of two parcels located north and south of an east-west intersecting drainage ditch and totaling about 53 acres. JEA acquired the southern parcel in 1977 to operate an electrical substation and wastewater facilities associated with the generating station. The past and present JEA operations and activities on this site did not cause the contamination that is the focus of the Corrective Measures Study (CMS) and subsequent remediation efforts; however, as the owner of the property, JEA is leading the effort to clean up the site.
Southern Parcel Site History & Operations
Operation of the wood treatment facility and the pipeline resulted in releases of wood treating preservatives and other petroleum based compounds on to the southern parcel. These releases affected soil, groundwater, and river sediments
Activities to Date
Over the past years, JEA has been diligent in investigating the distribution of the affected soil and groundwater, as well as sediments in the St. Johns River. JEA constructed a Groundwater Recovery System along the KGS shoreline of the St. Johns River in 2012 as an interim measure to prevent affected groundwater from migrating into the river. The Groundwater Recovery System began operations in January 2013 and continues operation today.
Proposed Remediation Plan for the Site
JEA completed a draft CMS in June 2013 to develop, evaluate, and recommend corrective measures alternatives that address the environmental concerns in a manner that is technically feasible and cost effective. It is important to select alternatives that represent the best use of public funds for the protection of human health and the environment at KGS. The CMS outlines remedial action goals for all contaminated soil, groundwater, and sediments. These goals will be used to measure and evaluate the performance of the proposed remedy.
Working closely with FDEP and the adjacent property owners, JEA revised and updated the CMS in August 2014. The proposed remedies for the affected soils, groundwater, and sediments are summarized in this fact sheet. The proposed remedies for both soil and groundwater will restrict the future land use of the KGS and the adjacent properties to commercial or industrial use and prohibit the use of shallow groundwater in the area. Engineering controls are also proposed to limit human exposure to contaminated soils and restrict the migration of contaminated groundwater into the St. Johns River.
Soil Proposed Remedies:
• Capping identified areas with an asphalt layer; and
• Removing and disposing of surface soils from the property adjacent to the KGS.
Groundwater Proposed Remedies:
• Continuing operation of the existing groundwater recovery system; and
• Field testing (and potential use of) a subsurface extraction method to remove creosote-like fluids from the groundwater beneath the southeastern part of the site.
Sediments Proposed Remedies:
• Removing high concentration areas of creosote contaminated sediments and replacing removed sediments with clean fill dirt;
• Placing the removed sediments inside a designated dredge area prior to burying and capping sediments with asphalt onsite; and
• Monitored natural recovery of the remaining sediments, which will be remediated by natural physical, chemical, and biological processes until remedial goals are attained.
Current Status and Project Schedule
Public Outreach and Additional Information
Matt McClure – (904) 665-6253
Jaclyn Taricska – (904) 665-4243
Even Better Power Reliability
JEA's state-of-the-art technology identifies customers and neighborhoods in need of electric reliability improvements.
Contact
-
If you have any questions about the JEA Kennedy Generation Station Site - Corrective Measures Study, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.
Related Links
-
2014.12.03 Town Hall Meeting - Kennedy Generating Station Corrective Measures Study
JEA and the Florida Department of Environmental Protection (FDEP) would like to invite you to an informational meeting to discuss tentative plans for environmental remediation at JEA’s Kennedy Generating Station located at 4215 Talleyrand Avenue.
-
Frequently Asked Questions
00422156-1 1 Frequently Asked Questions Corrective Measures Study Former Wood Preserving Area JEA -Kennedy Generating Station Jacksonville, Florida December 2014 JEA proposes to implement corrective measures to clean up soil, groundwater, and sediments affected by previous owners of a wood treating operation located on