Estimated Dates & Work Schedule

Anticipated Start Date: 2021-10-18
Anticipated End Date: 2021-12-17

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, evening hours and weekends may be necessary. 

Project Objective

A contractor working for JEA (Callaway Contracting, Inc.) replaced a portion of aging sanitary sewer main along Kuralei Drive between Mindanao Drive and Indies Drive East, and at the intersection of Kuralei Drive and Indies Drive East. These pipes had reached the end of their useful service lives and needed to be proactively replaced to ensure the reliability of the JEA sewer system in the area. Failures to sewer mains can potentially cause sewer back-ups, environmental harm and roadway issues. 

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights-of-way, roads and easements. 

Restoration of the Project Area

Restoration of the project area typically will begin 2-3 weeks after the new sewer line has been installed, tested and cleared for use.  Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition. 

Map of the Project Area

Kuralei Dr Map