Lake Shore Boulevard Sewer Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-10-06
Anticipated End Date: 2018-10-26

Monday through Friday from 7:00 a.m. to 5:00 p.m.   

NOTE: Start and completion dates are subject to change and in some circumstances weekend and evening hours may be necessary.  

Project Objective

JEA crews completed installation of a new sanitary sewer tap near 1218 Lake Shore Boulevard. 

Construction Conditions

Construction occurred in the City’s streets, rights of way and easements.

Road Closure and Detour

For the safety of our crews and the general public, JEA will be required to temporarily detour traffic on Lake Shore Boulevard while this work is completed.  Residents will be permitted to drive with caution through the construction area. Please observe all detour and road closure signs, as well as general instructions provided by the crew.  

Restoration of Project Area

Restoration of the project area will begin after the sewer tap has been installed, tested, cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.