McCormick Road FDOT Paving Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-12-06
Anticipated End Date: 2018-12-10
This project has been completed as of December 9, 2018.

Roads Affected

McCormick Road between Monument Road and Kernan Boulevard

Project Objective

A contractor working for the Florida Department of Transportation (FDOT) has repaired and repaved a portion of McCormick Road between Monument Road and Kernan Boulevard following recent repairs to a water main damaged by a Verizon contractor.  

Detour Information

For the safety of crews and the general public, the FDOT contractor was required to temporarily detour both lanes of eastbound traffic on McCormick Road (SR-116) from Thursday, December 6th at 8:30 a.m. through Sunday, December 9th at 11 p.m.  

Additional Information

McCormick Paving - Detour Route