Estimated Dates & Work Schedule

Anticipated Start Date: 2018-11-05
Anticipated End Date: 2018-11-30

Monday through Friday 7:00 am to 4:00 pm

Note: Start and completion dates are highly subject to change and in some circumstances, weekend and evening hours may be required. Crews will not be working on November 12th, 22nd, and 23rd in observance of City of Jacksonville holidays.

 

Project Objective

JEA replaced a portion of a sanitary sewer main from 6943 Moncrief Road West to 6663 Gillislee Drive West. Failures to sewer lines can potentially cause major sewer back-ups and roadway issues.  

Construction Conditions

Construction will occur in the City’s streets, rights of way and easements. This work required the removal of ground water with pump systems prior to construction. These pump systems operated continuously during the repairs.

Restoration of Project Area

Restoration of the project area will begin after the sewer line has been replaced, tested and cleared for use. Upon completion of the project, existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be restored.  