N. Myrtle Street Emergency Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-10-31
Anticipated End Date: 2018-11-09

Normal working hours are Monday through Friday 7:00 to 4:00, however extended hours may be necessary. 

Roads Affected

Church Street, N. Beaver Street, N. Myrtle Avenue

Project Objective

JEA crews repaired a portion of a sanitary sewer main at 633 N. Myrtle Avenue between W. Beaver Street and W. Church Street. Failures to sewer mains can potentially cause major sewer back-ups and roadway issues. For the safety of our crews and the general public, a portion of N. Myrtle Avenue between W. Beaver Street and W. Church Street was temporarily closed and traffic was detoured around the construction area. 

Detour Map

North Myrtle Street Detour Map