Norwich Road Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2021-05-24
Anticipated End Date: 2021-08-31

Monday through Friday, 8:00 a.m. to 5:00 p.m.*

*NOTE: In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews replaced and upgraded the existing water main on Norwich Road to Ardsley Road, and on Ardsley Road from Mundy Drive to San Jose Boulevard. This project will increase water pressure and provide improved system reliability to the area.  

Construction Conditions

Work was completed in City of Jacksonville rights-of-way and easements. 

Norwich Water Project Map

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the new water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways and/or sidewalks affected during construction will be returned to its pre-construction condition.