Oldfield Crossing Sewer Pump Station Upgrade

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-01-13
Anticipated End Date: 2020-05-31

Regular work hours: Monday through Friday from 7 a.m. to 4 p.m. 

Project Objective

A contractor working for JEA (Petticoat-Schmitt Civil Contractors, Inc.) upgraded the sanitary sewer pump station located at 4193 Oldfield Crossing Drive. This station is responsible for pumping wastewater from your neighborhood to JEA’s nearby Mandarin Wastewater Treatment Facility.  

This project involved expanding the existing station by adding additional pumps and equipment, installation of a new concrete pad and replacement of the exterior fencing. This project will increase the reliability of our sanitary sewer system.  

Construction Conditions

In order to complete this work, crews were required to install a temporary bypass piping system to ensure the proper flow of sewage to the nearby treatment facility during construction. Construction occurred in the City’s rights-of-way and easements.

Overall Project Area Map

Oldfield Crossing PS Project

Restoration of the Project Area

Restoration of the project area will begin once all construction activities have been completed. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.