Richmond Street Emergency Sewer Repair Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2021-05-17
Anticipated End Date: 2021-05-31

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*Note: In some circumstances, extended hours and weekends may be required. 

Project Objective

JEA crews repaired a portion of failing sanitary sewer line near 3626 Richmond Street. This repair was necessary to ensure the reliability of the sewer system that serves your neighborhood.  Failures to sewer lines can potentially cause major sewer back-ups, environmental harm and roadway issues.  

Construction Conditions

For the safety of our crews and the general public, we were required to temporarily detour traffic around the immediate work area to complete this work. Please see the work area map below.   

Richmond SIP Project Area Map

Restoration of the Project Area

Restoration of the project area began after the new sewer line has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction are returned pre-construction condition.