Seabreeze Drive Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2022-05-23
Anticipated End Date: 2022-07-31

Monday through Friday, 7:00. a.m. to 5:00 p.m.

Note: Start and completion dates are highly subject to change, and in some circumstances, extended hours and weekends may be required.

Project Objective

JEA replaced a portion of sanitary sewer main near 4444 Seabreeze Drive. This section of sewer main had reached the end of its useful service life and had to be proactively replaced to ensure the reliability of the sewer system that serves your neighborhood.  Failures to sewer mains can potentially cause major sewer back-ups, environmental harm and roadway issues.  

Construction Conditions

Construction occurred in City of Jacksonville rights-of-way and easements.

Project Map

Seabreeze Drive Sewer Improvement Project - Map

Restoration of the Project Area

Restoration of the project area will typically begin 2-3 weeks after the new sewer main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned pre-construction condition.