- Home
- In Our Community
- Construction Projects
- Soutel Drive Streetlight Installation Project
Soutel Drive Streetlight Installation Project
![](https://www.jea.com/uploadedimages/Images/ConstructionProjectDefaultBanner.jpg)
Estimated Dates & Work Schedule
Anticipated Start Date: 2019-09-25
Anticipated End Date: 2020-02-28
Anticipated End Date: 2020-02-28
Monday through Friday, 7:00 a.m. to 5:00 p.m. NOTE: In some circumstances, weekends and evening hours may be necessary.
Project Objective
Working in partnership with the City of Jacksonville, JEA installed sixty-six (66) new stand-alone wooden poles with LED streetlights along Soutel Drive from New Kings Road to Lem Turner Road. These new lights will be energy efficient and will provide for a brighter and safer community.
Project Area Map
Even Better Power Reliability
}
/uploadedImages/jeacom/SiteInterceptAdCEMI5.jpg
JEA's state-of-the-art technology identifies customers and neighborhoods in need of electric reliability improvements.
Contact
-
If you have any questions about the Soutel Drive Streetlight Installation Project, please contact JEA Project Outreach at (904) 665-7500 or email us at projectoutreach@jea.com.