St. Augustine Road Paving Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2015-03-25
Anticipated End Date: 2015-04-01
This project has been completed. Below is the information that was provided to customers prior to the project start date. 

Roads Affected

Inwood Terrace, Lorimier Road, St. Augustine Road

Project Objective

JEA has hired a contractor to mill and resurface the south bound travel lane of St. Augustine Road from Inwood Terrace to Lorimier Road. The contractor will also mill and resurface the intersection of Inwood Terrace and St. Augustine Road. This paving is included as part of the recently completed St. Augustine Road Water Improvement Project

Construction Areas

Please pay close attention to all posted construction signs and barricades. These signs will provide you an indication of where you can and cannot drive until the asphalt cools.

Construction Conditions

Driveways will be temporarily blocked for a short period while the asphalt is installed. The contractor will attempt to have all driveways accessible during evening and weekend hours. Once the necessary work is accomplished, crews will return access to your business or residence.