Tubman Drive North Water Main Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2019-07-02
Anticipated End Date: 2019-09-30

Monday through Friday from 7:00 a.m. to 5:00 p.m. NOTE: In some circumstances, weekends and extended hours may be necessary.

Project Objective

JEA crews replaced a portion of 6-inch water main line on Tubman Drive North. This work also included the installation of one (1) new fire hydrant. When completed, this project will increase water pressure and provide improved system reliability and fire protection.

Construction Conditions

Construction occurred in the City’s rights of way, streets and easements. 

Restoration of Project Area

Restoration of the project area will begin once the water main has been installed, tested and cleared for use. Upon completion of the project, any existing pavement, grass, driveways or sidewalks affected during construction will be returned to its pre-construction condition.

Project Area Map

Tubman Drive North WMIP