Union Street West Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-12-06
Anticipated End Date: 2024-01-05

Monday through Friday, 7:00 a.m. to 5:00 p.m.

*Dates are highly subject to change.

Project Objective

A contractor working for JEA (Murphy Pipeline) replaced portions of a sanitary sewer main line at 1314 Union Street West. This sewer line had reached the end of its useful service life and was proactively replaced to ensure the reliability of the sewer system. Failures to sewer lines can potentially cause major sewer back-ups, environmental harm and roadway issues. 

This project was completed using the pipe bursting method of construction. This method is less disruptive to neighborhoods than the traditional open-cut method of replacing sewer lines and the overall project duration is typically shorter. Watch a video to learn more about the pipe bursting process. Learn more at https://www.youtube.com/watch?v=W5JRzpwSbUs.

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way, roads, and easements.

Restoration of the Project Area

Restoration of the project area typically begins within 2-3 weeks after the sewer line has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their pre-construction condition.