W. 1st Street Emergency Sewer Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-10-20
Anticipated End Date: 2018-11-03

Normal working hours are Monday through Friday, 7 a.m. to 4 p.m. 

NOTE: Weekend and extended hours may be necessary to complete repairs. 

Roads Affected

Pearl Street North, Rudolph McKissick Sr. Boulevard, W. 1st Street

Project Objective

JEA crews repaired a failing portion of the sanitary sewer line on W. 1st Street between Rudolph McKissick Sr. Boulevard and Pearl Street North. Failures to sewer lines can potentially cause major sewer back-ups and roadway issues. 

Construction Areas

Construction occurred in the City's streets, rights of way and easements.  

Restoration of the Project Area

Restoration of the project area will begin after the sewer line has been repaired, tested and cleared for use. Upon completion of the project, existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be restored.