W. 21st Street Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-04-25
Anticipated End Date: 2023-08-31

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, extended hours and weekends may be required.

Project Objective

JEA crews upgraded and replaced the existing water main on W. 21st Street from Spires Avenue to the dead end of W. 21st Street. This section of water main had reached the end of its useful service life and was proactively replaced to ensure the reliability of the water system that serves your neighborhood. This work also included the installation of a new fire hydrant. This project will provide increased water pressure, enhanced fire protection and improved system reliability.

Construction Conditions

Construction primarily occurred in City of Jacksonville rights-of-way and utility easements.

Restoration of the Project Area

Restoration of the project area typically begins 2-3 weeks after the water main has been installed, tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways, or sidewalks affected during construction will be returned to their pre-construction condition. 

Map of Project Area

W. 21st Street Water Improvement Project