Wattle Tree Road West & Fern Tree Drive Emergency Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2018-11-30
Anticipated End Date: 2018-12-14

Monday through Friday, 7:00 a.m. to 5:00 p.m.

Note: Start and completion dates are highly subject to change and in some circumstances, weekend and evening hours may be required.   

Project Objective

JEA is repaired a portion of a sanitary sewer main at the intersection of Wattle Tree Road West and Fern Tree Drive. Failures to sewer lines can potentially cause major sewer back-ups and roadway issues.

Construction Conditions

Construction occured in the City’s streets, rights of way and easements. This work required the removal of ground water with pump systems prior to construction. These pump systems operated continuously during the repairs.

Restoration of Project Area

Restoration of the project area will begin after the sewer line has been repaired, tested and cleared for use. Upon completion of the project, existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be restored.

Wattle Tree Road West SIP - Detour Map