West Virginia Avenue Water Main Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2020-01-31
Anticipated End Date: 2020-04-30

Monday through Friday, 7:00 a.m. to 5:00 p.m. 

NOTE: In some circumstances, night weekend and extended hours may be necessary. JEA crews will not work on JEA holidays (2/17/20). 

Project Objective

JEA have completed a project to replace a portion of the potable water lines on West Virginia Court and on West Virginia Avenue, beginning at each end of Hema Road. This work also included the installation of two (2) new fire hydrants. This project will increase water pressure and provide improved system reliability and fire protection. 

Construction Conditions

Construction occurred in the City’s rights of way, streets and easements.  

Project Area Map

West Virginia Avenue Water Improvement Project Map

Restoration of the Project Area

Restoration of the project area will begin once the water main has been installed, tested and cleared for use. Upon completion of the project, any      existing pavement, grass, driveways or sidewalks affected during construction will be returned to its pre-construction condition.