Wildwood Road Water Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2016-04-01
Anticipated End Date: 2016-08-31
This project has been completed. Below is the information provided to customers prior to the project start date. 

Roads Affected

Carlotta Road South, Carlotta Road West, Townsend Boulevard, Wildwood Court, Wildwood Road

Project Objective

JEA crews will be replacing 1440 feet of the existing 6-inch water main on Wildwood Road, Carlotta Road South/West from Townsend Boulevard to Wildwood Road and Wildwood Court. When completed, this project will  increase water pressure and provide improved system reliability. Crews will also install 3 new fire hydrants to improve fire protection in the area.   

Construction Method

The contractor will primarily install the new water main with a technique called directional drilling. Directional drilling requires very little excavation, reduces construction duration, and is less disruptive to the surrounding community.  Once drilling operations are underway, it may be necessary for the contractor to work extended hours until the drill is complete.   

Construction Conditions

Construction will be done in the City’s rights of way and easements. There will be times when your road will have limited access while the water main is being installed.  

Water Outages

Some customers will experience minor interruptions to their water service.  JEA will notify customers 48 hours prior to any planned outages. Residents may also experience a brief (10 to 15 minutes) outage while crews transfer your home from the old water service to the new water service.

Restoration of Project Area 

Restoration of the project area will begin once the water lines are installed and have been tested and cleared for use. Upon completion of the project, any existing pavement, grass, driveways or sidewalks affected during construction will be returned to its pre-construction condition.