Winrock Drive Sewer Improvement Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2016-05-04
Anticipated End Date: 2016-06-30

Roads Affected

Sandusky Drive East, Sandusky Avenue South, Winrock Drive North, Winrock Drive West

Project Objective

JEA crews replaced a 120 foot section of 8-inch failing sanitary sewer main on Winrock Drive West.  

Conditions During Construction

Construction primarily occurred in the City’s rights of way and easements.   

Detour Route

From Winrock Drive North, traffic will turn right at Sandusky Avenue East, right on Sandusky Avenue South, then right on Winrock Drive West. 
From Winrock Drive West, traffic will turn left at Sandusky Avenue South, left on Sandusky Avenue East, then left on Winrock Drive North. 

Restoration of Project Area 

Restoration of the project area began after the sewer main has been installed and the dewatering system removed. Upon completion of the project, any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned to its pre-construction condition.