Harlow Boulevard Sanitary Sewer Lining Project

Estimated Dates & Work Schedule

Anticipated Start Date: 2023-03-20
Anticipated End Date: 2023-04-30

Monday through Friday, 7:00 a.m. to 5:00 p.m.*

*In some circumstances, evening hours and weekends may be required. 

Project Objective

A contractor working for JEA (Vortex Companies) replaced portions of the sanitary sewer lines on portions of Harlow Bouelvard, Anvers Boulevard, Macgregor Drive and Cinderella Road. These existing sewer lines had reached the end of their useful service lives and were proactively replaced to increase the reliability of the sewer system and to prevent any future sewer main breaks. Failures to sewer lines can potentially cause major sewer back-ups, environmental harm and roadway issues.  

This project was completed using a trenchless lining technology that allows for the rehabilitation of the existing pipe with minimal disruption to the community. This technology also reduces the amount of time it would take to complete a similar project using traditional construction methods. Visit https://youtu.be/EkVTnfUpMjA to watch a video about the process. 

Construction Conditions

Construction primarily occurred in the City of Jacksonville rights-of-way, roads and easements.

 Sweetwater Manhole Lining Project Area Map

Restoration of the Project Area

Restoration of the project area typically begins 2-3 after the manhole linings have been completed, and the manholes have been tested and cleared for use. Any existing pavement, grass, curb, gutter, driveways or sidewalks affected during construction will be returned pre-construction condition.